既有线顶进涵施工技术
引用本文:谭波.既有线顶进涵施工技术[J].企业技术开发,2011(21):18-20.
作者姓名:谭波
作者单位:中铁五局(集团)公司;
摘    要:文章结合浙赣铁路电气化改造工程第十二标段顶进涵施工,介绍了顶进涵施工工艺,并重点对既有线顶进涵滑板、后背施工、D型便梁施工、顶进过程中的控制措施进行了阐述。

关 键 词:既有线  顶进涵  施工

Construction technology of the jacking culvert of existing lines
TAN Bo.Construction technology of the jacking culvert of existing lines[J].Technological Development of Enterprise,2011(21):18-20.
Authors:TAN Bo
Institution:TAN Bo (China Railway No.5 Engineering Group Co.,Ltd.,Changsha,Hunan 410117,China)
Abstract:Combined with the jacking culvert construction of the 12th section of Zhejiang-Jiangxi Railway electrification transformation project,this paper introduces the technology of jacking culvert construction,and emphatically explains the slide plate of jacking culvert of existing lines,back construction,D-type auxiliary girder construction and the control measures in jacking process.
Keywords:existing llines  jacking culvert  construction  