关于人工挖孔灌注桩过程控制的探讨 |
| |
引用本文: | 许毓红.关于人工挖孔灌注桩过程控制的探讨[J].中小企业科技,2010(11):38-39,46. |
| |
作者姓名: | 许毓红 |
| |
作者单位: | 广西建工集团第三建筑工程有限责任公司,广西柳州545002 |
| |
摘 要: | 文章介绍了"中房·金泰苑"基础工程人工挖孔灌注桩的施工工艺,总结了在孔桩施工过程中采取的一些质量控制措施,以供广大工程技术人员参考。
|
关 键 词: | 人工挖孔桩 工艺 质量控制 |
A Probe into Process Control of Manually Excavated Cast-in-place Pile |
| |
Authors: | XU Yu-hong |
| |
Institution: | XU Yu-hong (The Third Construction Engineering Limited Liability Company of Guangxi Construction Engineering Group,Liuzhou Guangxi 545002) |
| |
Abstract: | The paper introduces the construction techniques of the manually excavated cast-in-place pile of"Zhongfang Jintai Garden"foundation construction project,and summarizes some quality controlling measures that should be adopted in pile construction,for the reference of many engineering technicians. |
| |
Keywords: | manually excavated cast-in-place pile techniques quality ocontrol |
本文献已被 维普 等数据库收录! |