山秀水电站升压站优化设计
引用本文:周逸萍.山秀水电站升压站优化设计[J].企业科技与发展,2009(10):168-169.
作者姓名:周逸萍
作者单位:南宁水利电力设计院,广西南宁530001
摘    要:山秀水电站的升压站优化布置方案在节省土建及设备投资、满足安全运行的前提下,把110kV GIS布置在变压器硕上。这种做法节省综合造价约52%,缩短工期,可实现提前发电1个月。采用该方案,水电站至今运行良好,取得很好的经济效益,可作为类似工程的参考。

关 键 词:水电站  电气设备布置  110  kVGIS  户外布置

The Optimum Design of Booster Station at Shanxiu Hydropower Station
Authors:Zhou Yi-ping
Institution:Zhou Yi-ping ( Nanning Water Conservancy and Electric Power Design Institute, Nanning Guangxi 570001 )
Abstract:Based on the saving civil engineering and equipment investment, and safe operation, the optimum design of booster station at Shanxiu Hydropower Station puts 110 kV GIS on the top of transformer. In this way, 52 percent of costs can be saved, while construction period can be cut and the electric power can be generated one month in advance. After adopting this plan, the hydrnpower station is running well and obtains some good economic benefits, as the reference of similar projects.
Keywords:hydropower station  electric equipment placement  100 kV GIS  outdoor placement