500万吨炼钢工程项目施工的策划和实施
引用本文:刘顺宝.500万吨炼钢工程项目施工的策划和实施[J].价值工程,2009,28(9):94-97.
作者姓名:刘顺宝
作者单位:中冶京唐建设有限公司邯钢项目部,邯郸,056003
摘    要:介绍了邯钢新区2座顶底复吹转炉、2座双流板坯连铸机、双工位LF精炼炉、双工位RH精炼炉、铁水倒灌站、贴水预处理以及废钢间、公辅5大除尘系统、废钢间、炉渣间、公辅给回水、各种介质管道等的总体策划、安排及施工顺序,保证了工程均衡、有序、安全施工。

关 键 词:策划  统筹安排  施工顺序

To Disign and to Practise on the Five Million Ton Steal-Smelting Project
Liu Shunbao.To Disign and to Practise on the Five Million Ton Steal-Smelting Project[J].Value Engineering,2009,28(9):94-97.
Authors:Liu Shunbao
Institution:MCC Jing-Tang Construction Limited Company;Project Department of Han-Gang;Handan 056003;China
Abstract:This article describe the main plan of Han-Gang new area,arrangements and construction sequence of 2 top and bottom combined blown converter,2double flow slab,twin LF,duplex RH top plant,iron pot stand down,pretreatment of hot metal and scrap house,5 dedusting system of public auxiliary,scrap house,slag house,recycled water of pubic auxiliary,all kinds of media piping in handan iron and sreel new area.It assured a balance,orderly and safety construction.
Keywords:plan  plan in entirety  construction sequence  