海子湖围堰粉喷桩施工试验研究 |
| |
引用本文: | 李鹏,;李修磊,;黄永金,;陈崇德. 海子湖围堰粉喷桩施工试验研究[J]. 湖北水力发电, 2014, 0(5): 22-25 |
| |
作者姓名: | 李鹏, 李修磊, 黄永金, 陈崇德 |
| |
作者单位: | [1]湖北省漳河工程管理局,湖北荆门448156; [2]湖北路达胜工程技术咨询有限公司,湖北武汉430070 |
| |
摘 要: | 海子湖围堰进行了粉喷桩工艺试验,介绍试验方案、质量控制措施、动力触探法、钻孔取芯和开挖检查等方法,对试验结果进行检测。根据试验检测结果确定了粉喷桩施工工艺及各项技术参数。
|
关 键 词: | 海子湖 围堰 引江济汉 粉喷桩试验 |
Experimental Study on the Construction Technology of Powder Spraying Pile in Haizi Lake Cofferdam |
| |
Affiliation: | LI Peng, LI Xiulei, HUAN Yongjin, CHEN Chongde (1. Hubei Zhanghe Project Management Bureau, Jingmen 448156, China; 2. Hubei Ludasheng Engineering Technology Consultation Co. , Ltd. , Wuhan 430071, China) |
| |
Abstract: | An experimental study on the construction technology of powder spraying pile was carried out in the cofferdam of Haizi Lake .The experiment scheme , quality control measures , dynamic penetration method , core drilling and exca-vation inspection methods are introduced .According to results of the experimental tests , construction technology and technical parameters that should be adopted are determined . |
| |
Keywords: | Haizi Lake cofferdam water diversion works from the Yangtze river to the Hanjiang river powder spra-ying pile test |