蒲石河抽水蓄能电站输水系统充排水试验方法
引用本文:周翰青.蒲石河抽水蓄能电站输水系统充排水试验方法[J].水利水电技术,2015,46(5):86.
作者姓名:周翰青
作者单位:(中国人民武装警察部队水电第二总队六支队,福建厦门361021)
摘    要:高水头大型抽水蓄能电站输水系统的充水和排水,是电站投入运行不可缺少的一项安全检验,初期充排水试验是加载、卸载、检查、监测、发现问题和处理缺陷的过程,为今后电站正式运行提供安全可靠的质量保证。本文详细介绍了辽宁蒲石河抽水蓄能电站输水系统充排水试验方法,可供类似工程参考。

关 键 词:抽水蓄能  充排水  引水系统  尾闸  
收稿时间:2014-12-30

Method for water filling and discharging test on water delivery system of Pushihe Pumped Storage Hydropower Station
ZHOU Hanqing.Method for water filling and discharging test on water delivery system of Pushihe Pumped Storage Hydropower Station[J].Water Resources and Hydropower Engineering,2015,46(5):86.
Authors:ZHOU Hanqing
Institution:(The No.6 Branch of the No.2 General Team of Armed Police Hydropower Troops, Xiamen361021, Fujian, China)
Abstract:The water filling and discharging of the water delivery system for the large pumped storage hydropower station with high head is an absolutely necessary safety testing for putting it into operation. The initial water filling and discharging test is a process of loading, unloading, inspection, monitoring,problem finding and defect treating, which provides a safe and reliable quality guarantee for its commercial operation in the days to come. The Method for water filling and discharging test on water delivery system of Pushihe Pumped Storage Hydropower Station is described herein in detail, so as to provide reference for the similar projects concerned.
Keywords:pumped storage hydropower station  water filling and discharging  water delivery system  tailrace gate      