拔贡水电站改扩建工程二期施工导流围堰优化施工
引用本文:谢一清,刘刚,梁梅芳.拔贡水电站改扩建工程二期施工导流围堰优化施工[J].红水河,2013(6):26-30,44.
作者姓名:谢一清  刘刚  梁梅芳
作者单位:广西水电工程局,广西南宁530001
摘    要:文章阐述了拔贡水电站改扩建工程二期施工导流围堰施工优化方案,结合工程实际情况及特点,合理布置,采取有效措施,顺利完成了二期施工导流围堰施工,为二期基坑开挖创造了良好前提条件。

关 键 词:围堰  导截流  拔贡水电站改扩建工程

Optimization on Phase-II Diversion Cofferdam Construction Scheme for Extension Project of Bagong Hydropower Station
XIE Yi-qing,LIU Gang,LIANG Mei-fang.Optimization on Phase-II Diversion Cofferdam Construction Scheme for Extension Project of Bagong Hydropower Station[J].Hongshui River,2013(6):26-30,44.
Authors:XIE Yi-qing  LIU Gang  LIANG Mei-fang
Institution:(Guangxi Hydroelectric Construction Bureau, Nanning, Guangxi, 530001 )
Abstract:The paper makes an introduction to the construction optimization scheme for the phase-II diversion coffer- dam of the extension project of Bagong hydropower station. The construction of the phase-II diversion cofferdam is completed successfully by combining the actual situations and characteristics of the project with reasonable arrange- ment and effective measures, which creates favorable preconditions for the phase-II pit excavation.
Keywords:cofferdam  construction diversion and closure  Extension Project of Bagong Hydropower Station