缅甸工程如何实现中方人员、材料、机具设备入境 |
| |
引用本文: | 梁跃清,王文君.缅甸工程如何实现中方人员、材料、机具设备入境[J].企业科技与发展,2011(2):19-21. |
| |
作者姓名: | 梁跃清 王文君 |
| |
作者单位: | 湖北省电力勘测设计院,湖北武汉430024 |
| |
摘 要: | 文章结合从事缅甸某输电线路工程的人员、材料与机具设备进出口的申报、计划、控制、协调等工作,总结了一系列关于人员、材料、机具设备进入缅甸的实际有效方法和经验,并期待这些方法和经验对今后类似跨国工程有一定的参考价值。
|
关 键 词: | 缅甸工程 入境 申报 计划 物流程序 |
How Chinese Personnel,Materials, Machinery and Equipment to Enter Myanmar |
| |
Authors: | LIANG Yue-qing WANG Wen-jun |
| |
Institution: | (Hubei Electric Power Survey and Design Institute, Wuhan Hebei 430024) |
| |
Abstract: | By engaging in the work of the import and export declaration, planning, control and coordination of personnel, materials, equipment of Myanmar Dagon Nickel transmission line project, the article concluded a series of practical and effective experiences about them, for the reference of similar cross-boarder projects in the future. |
| |
Keywords: | Myanmar project enlry country declaration plan logistics process |