小峰水库主坝防渗工程施工难点及对策 |
| |
引用本文: | 张丽萍.小峰水库主坝防渗工程施工难点及对策[J].企业科技与发展,2010(11):208-209. |
| |
作者姓名: | 张丽萍 |
| |
作者单位: | 广西水利电力勘测设计研究院,广西南宁530023 |
| |
摘 要: | 小峰水库主坝为均质土坝,由于施工质量问题而出现坝体渗水。为使水库能正常蓄水,水库管理部门曾对大坝进行过3次较大规模的加固,前2次加固效果均不理想,第三次加固效果则基本达到设计要求。文章主要针对第三次加固施工中出现的问题进行分析和探讨。
|
关 键 词: | 灌浆 施工 难点 对策 小峰水库 |
Difficulties and Solutions of the Main Dam Seepage Control Project in Xiaofeng Reservoir |
| |
Authors: | ZHANG Li-ping |
| |
Institution: | ZHANG Li-ping (Guangxi Water Conservancy and Electric Power Investigation Design and Research Institute,Nanning Guangxi 530023 ) |
| |
Abstract: | The main dam of Xiaofeng Reservoir is homogeneous earth dam and has seepage due to construction problem. To restore the reservoir,the reservoir department had 3 large-scale reinforcements,among which the first two were not good while the third basically reached the designed requirement.The article illustrates and analyzes mainly the problems which occurred in the third reinforcement. |
| |