百色水利枢纽下闸蓄水方案研究
引用本文:邱振天,何素明. 百色水利枢纽下闸蓄水方案研究[J]. 广西水利水电, 2007, 0(2): 6-9,13
作者姓名:邱振天  何素明
作者单位:广西水利电力勘测设计研究院,广西,南宁,530023
摘    要:针对百色水利枢纽由于移民搬迁滞后推迟到汛末下闸的问题,从各个方面对下闸蓄水方案进行分析研究后,决定于2005年8月26日下闸蓄水,使得2006年6月26日水库能蓄水到195 m,7月15日第一台机组顺利发电,达到了预定目标.

关 键 词:下闸  蓄水  研究  评价  百色水利枢纽
文章编号:1003-1510(2007)02-0006-04
收稿时间:2007-01-25
修稿时间:2007-01-25

Study of impoundment scheme for Baise Multipurpose Dam Project
QIU Zhen-tian,HE Su-ming. Study of impoundment scheme for Baise Multipurpose Dam Project[J]. Gx Water Resources & Hydropower Engineering, 2007, 0(2): 6-9,13
Authors:QIU Zhen-tian  HE Su-ming
Affiliation:Guangxi Water and Power Design Institute, Nanning 530023, China
Abstract:The gate closing date of Baise Multipurpose Dam Project was postponed till the end of flood season due to sluggish inhabitant resettlement. After studying the impoundment scheme in all aspects, it was determined to close gate and start impoundment on August 26 of 2005, which made the reservoir level was up to 195m on June 26 of 2006, the first turbine generator unit was put into operation smoothly on July 15 of 2006 as scheduled.
Keywords:Close gate   impoundment   study   appraise  Baise Multipurpose Dam Project