闸墩门槽二期整体式滑模施工技术
引用本文:覃儒开.闸墩门槽二期整体式滑模施工技术[J].中小企业科技,2010(6).
作者姓名:覃儒开
作者单位:广西水电工程局恒美晖设计公司;
摘    要:长洲水利枢纽外江泄水闸工程是整个外江工程关键性工期的保证工程,由于遭遇2006年洪水,外江工程进度严重滞后,需要对原施工方案进行优化。整体式滑模施工技术具有施工进度快,保证二期混凝土施工质量,克服了常规单边门槽滑模的缺点等优势,据此,文章阐述了整体式滑模施工的技术要点。

关 键 词:整体式  滑模  闸墩门槽  施工技术  

Integral Slip Form Construction for Second Stage Pier Gate
Authors:QIN Ru-kai
Institution:QIN Ru-kai (Hengmeihui Design Company,Guangxi Hydroelectric Engineering Bureau,Nannning Guangxi 530001)
Abstract:The out falling sluice of Changzhou water conservancy hub is a guarantee project for the overall outer river project. The progress has been affected by the flood in 2006,so the original construction needs to be optimized.The high efficiency of the integral slip form construction can ensure the quality of second stage concrete,and it also avoids the general flaw of the single-sided slip form.The article introduces the technical features of the slip form construction.
Keywords:integral  slip form  pier gate  construction technique  