工程延误慎言“罚”
引用本文:杨志勇,高景泉.工程延误慎言“罚”[J].水利经济,2007,25(3):51-52.
作者姓名:杨志勇  高景泉
作者单位:1. 河海大学商学院,江苏,南京,210098
2. 浙江水专工程建设监理有限公司,浙江,杭州,310016
摘    要:针对工程合同条款中经常出现的发包人对承包商误期违约“罚款”条款,分析了罚款、惩罚性赔偿和惩罚性违约金的法律性质,认为在合同中约定罚款难以得到法律的保护,只有在合同中清晰、准确地约定误期违约责任的性质,发包人才能快速获得赔偿,避免发生争议。

关 键 词:工程延误  误期赔偿  罚款  惩罚性赔偿  惩罚性违约金
文章编号:1003-9511(2007)03-0051-02
收稿时间:2006-09-18
修稿时间:2006-09-18

On penalty for delay of works
YANG Zhi-yong.On penalty for delay of works[J].Journal of Economics of Water Resources,2007,25(3):51-52.
Authors:YANG Zhi-yong
Abstract:With regard to the penalty clauses,which prescribe that the contractors shall pay to the employers,for delay of works in the works contracts,the legal characters of penalty,punitive damages and penalty for breach of contracts are analyzed.It is regarded that the penalty stipulations in the contracts are difficult to be protected by laws,only is the character of delay or breach of contracts clearly stipulated in the contracts,the contractors can rapidly get their damages,and thus possible disputes will be avoided.
Keywords:delay of works  damages for delay  penalty  punitive damages  penalty for breach of contracts