Factors Causing Design Schedule Delays in Turnkey Projects in Taiwan: An Empirical Study of Power Distribution Substation Projects
Authors:Nie‐Jia Yau  Jyh‐Bin Yang
Institution:Graduate Institute of Construction Engineering and Management, National Central University, Jhongli City, Taiwan
Abstract:Because of its benefits, the turnkey project delivery method has received much global attention; however, turnkey contractors often have difficulty completing projects within the contract schedule. Through case studies, expert interviews, questionnaire surveys, and statistical data analysis, this study revealed that, of 27 delay factors that affect design schedules in power distribution substation projects, the most common delay factors are “public contending or political involvement” and “tedious review processes of government agencies.” Furthermore, the study proposes assorted strategies from the perspectives of the owner, turnkey contractor, and designer that can be used to help prevent delays in similar turnkey projects.
Keywords:turnkey project  public‐private partnership  planning and design  schedule delay  power distribution substation
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号